Till the end of 2024, the PE Service performed a a TOTAL of 4,095 MWD of Technical Site Activities, as SUPERVISON to ASSEMBLING for Mechanical Supervision, Electrical Supervision Equipment Installation including On Site test Start-Up Activities executed by the PE Team, a multi cultural, multi language and multi nations group of people formed by specialized […]
Official attendance registers of Activities Executed at Kirklareli Plant in TURKEY report Vendor Completed the Scope of the Vendor in 12 WEEKS as per Project Schedule, despite PE Service working in extreme environmental conditions (-10 °C in winter, +35 °C in Summer) a TOTAL of 412 MWD as EXTRA Man Working Days about 4,225 […]
Official register for ASSEMBLING and Start-Up Activities Executed for the Kirklareli Plant in TURKEY reports TOTAL Man Working Days 1,098 MWD TOTAL Working HOURS about 11,255 Hours performed on SITE by PE Service and the PE Team Overall DATA accounted since the Assembling up to Commercial Production