Official attendance registers of Activities Executed at Kirklareli Plant in TURKEY report

  • Vendor Completed the Scope of the Vendor in 12 WEEKS as per Project Schedule, despite PE Service working in extreme environmental conditions (-10 °C in winter, +35 °C in Summer)
  • a TOTAL of     412 MWD      as     EXTRA Man Working Days
  • about             4,225 Hours

 

ASSEMBLING Data accounting performed since January 2023 when Assembling Supervision started

 

Extra MWD caused by BUYER suppliers delivery delays, local materials out of specifications as well as local jobs executed forcing the Vendor to correct BUYER Sub-vendors non-conformities